New Hire at the Pen Factory

What is the registration order of standard information?

Standard information registration order

It's time to enter standard information. If you don't have the previous one, you can't add the latter one.

What it means

The reference information leans against each other. You must have items to create a BOM, and you must have a BOM and process sequence to issue work orders.

So, when opening a new factory, we make a checklist of what needs to be registered first.

At the pen factory

The order in a ballpoint pen factory is Item → BOM → Process Sequence → Work Order. From day 1 to day 16, the order is the same as in factory No. 1.

Why it matters

If you don't know the order, you won't know what's missing.