What is Material Requirements Planning?

MRP, Material Requirements Planning

Calculating how many materials are needed and by when to make it as planned.

What it means

Material requirement planning is a calculation that collects everything included in the production plan, calculates the required quantity of each material using the BOM, and subtracts existing inventory and incoming orders to find any shortages. It is called MRP in English abbreviation.

The key is that it is calculated “all at once.” If you count each order separately, multiple orders for the same inventory will count as their own.

At the pen factory

On the 8th day, Assistant Manager Choi counts each order separately and says "black refill 10 pieces short." When I put it together in one table, I need 200 pieces for two days, but there are 140 pieces in stock, so I am 60 pieces short, and it will run out on November 9th.

Why it matters

Knowing in advance what to buy and when can prevent the factory from shutting down due to lack of materials. For calculations to be correct, the BOM, plan, and inventory must all be accurate.

How this differs from Production plan

The production plan is “when and how many products to make,” and the material requirement plan takes that plan and calculates “when and how many materials are needed.”